Developer StatementWright family / project land interests
Public project materials identify the Wright family as the landowner/development sponsor. Parcel ownership and the legally responsible project entity should be verified phase by phase through deeds and executed agreements.
Sources R13–R16, R20–R23
Developer StatementAzure Energy / Azure Engineering
Azure Engineering lists Project River and describes feasibility/conceptual work plus future preliminary engineering and permitting. Exact contractual scope, engineer-of-record status, EPC responsibility, and performance guarantees remain important open evidence requests.
Sources R17–R19
Government StatementAlgorhythm Holdings
An SEC filing confirms Algorhythm’s Sept. 15 acquisition transaction involving Azure Energy. The filing establishes the corporate transaction; it does not by itself establish what obligations Algorhythm has assumed toward Project River.
Sources R18–R19
Government StatementCity of Cleveland
The city controls municipal annexation/zoning proceedings within its authority and announced the temporary suspension of direct Project River meetings pending an engineering review.
Sources R01–R04
Government StatementBradley County
County records, zoning, planning history, roads, parcel data, and prior annexation/interlocal records remain relevant to the site and surrounding unincorporated community.
Sources R05, R10–R12
Government StatementTDEC, TDOT, TVA / utilities
Environmental permits, traffic/access approvals, and utility/interconnection arrangements are distinct from city land-use approval. The responsible agency depends on the specific facility component and filing.
Sources R07–R11, R13